Differences
This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision Next revision | Previous revision | ||
| log [2026/03/30 11:58] – team2 | log [2026/04/20 10:03] (current) – team2 | ||
|---|---|---|---|
| Line 30: | Line 30: | ||
| We also had a presentation in Communication where we showed off our first logo and flyer draft. It didn’t go exactly as planned because we had just decided to change our project’s name. Presenting an outdates flyer definitely wasn't our best look but it was a good reality check on how fast things are moving. | We also had a presentation in Communication where we showed off our first logo and flyer draft. It didn’t go exactly as planned because we had just decided to change our project’s name. Presenting an outdates flyer definitely wasn't our best look but it was a good reality check on how fast things are moving. | ||
| + | |||
| + | ==== 5th Week Report ==== | ||
| + | |||
| + | In week 5, we focused on the project development chapter as well as on Jira. During this time, we planned in more detail which tasks need to be completed before the interim deadline in April. In addition, we created detailed schematics. However, we still need to continue working on how we want to implement all the electrical components. On the other hand, we also completed more detailed structural drawings. Based on these, we were able to decide on a more final shape for the capsule, as well as define the material layers and what should be included. Beside of that, we worked on a presentation about an ethical scandal, as well as a joint presentation summarizing all the work completed so far for the marketing and communication courses. | ||
| + | |||
| + | ==== 6 + 7th Week Report ==== | ||
| + | During the Easter break, we focused on preparing the interim presentation. We discussed which aspects are most important and how to present them effectively, | ||
| ===== Meetings ===== | ===== Meetings ===== | ||
| Line 115: | Line 122: | ||
| === Minute: === | === Minute: === | ||
| + | Minute: | ||
| + | The professors provided guidance on the interim presentation and report requirements: | ||
| + | - Interim Presentation: | ||
| + | - Report Formatting: Describe every image and table in the text before they appear. Remove all titles/ | ||
| + | - Terminology: | ||
| + | - Glossary: Complete the list of acronyms and technical terms. | ||
| - | ==== 6th Meeting (2026-03-31) ==== | + | Considerations for our product: |
| + | - Structure: Use heat to bend the wooden beams for the shell. Continue investigating screw-free Japanese joinery methods. | ||
| + | - Airflow: Use a quiet 12V fan (will require a voltage drop circuit). Consider regulated openings at the bottom for natural airflow, as high noise cancellation and high airflow are difficult to achieve together. | ||
| + | - Smart System: The microcontroller needs WiFi to sync the mobile app with the lighting and music. | ||
| + | - Audio: The speaker should be a standalone WiFi/ | ||
| + | - Power: LED strips | ||
| + | |||
| + | ==== 6th Meeting (2026-04-01) ==== | ||
| === Agenda: === | === Agenda: === | ||
| - | | + | |
| - Software Development Idea | - Software Development Idea | ||
| - Plans for next week | - Plans for next week | ||
| === Minute: === | === Minute: === | ||
| + | The professors provided more feedback on the detailed schematics, they also suggested the usage Raspberry Pi because it supports more features | ||
| + | - Reference in the report table figures | ||
| + | - The materials voltage matching voltages and detailed schematics power supply | ||
| + | |||
| + | ==== 7th Meeting (2026-04-16) ==== | ||
| + | === Agenda: === | ||
| + | - Interim Presentation | ||
| + | |||
| + | === Minute: === | ||
| + | This week, we had our interim presentation. We presented the topics we have already worked on. Some of the key focus points for the final presentation are clearly how we communicate our content. | ||
| + | No reading directly from the slides, face the audience, and present calmly but with energy. At the beginning of the presentation, | ||
| + | We need larger headings on our slides. We might also rearrange the order so that project management comes at the end. Pedro will send his comments by email. | ||
| + | | ||
| ===== Activities ===== | ===== Activities ===== | ||
| //Please register here all accomplished project activities// | //Please register here all accomplished project activities// | ||